Subcontracting Opportunities
SSH is committed to working closely with the Foothill Gold Line Construction Authority to ensure that this project successfully meets and exceeds the project’s 14.9% Small Business Enterprise (SBE) goal.
CONSTRUCTION MILESTONES
Preconstruction NTP | June 2026 | 18 months
Construction NTP | Dec. 2027 | 36 months
System Testing Start | Dec. 2030 | 10 months
Ready for Operation | Oct. 2031
FUTURE BID OPPORTUNITIES – ANTICIPATED Q3 2027
Surveying
Environmental Consulting/Monitoring
Traffic Control
Erosion Control
Temporary Facilities
Material Testing
Site Clearing
Demolition
Hauling
CIDH Foundations
Driven Piles
Post Tensioning
Small Material Supply Packages
Drainage
Utility Relocation/Support
Trackwork Preparation
Directional Boring
Concrete Flatwork
Signage
Striping
Landscaping
MSE Panel Supply
Precast Soundwall Post & Panel Supply
Track Material Supply
Specialty Concrete
Fencing & Railing
Equipment/Material Supply
HMA Paving
Final Striping
Cleanup
Punch List Items
Select Specialty Sub Scopes
Architectural Finishes
Bar Reinforcing Steel
Waterproofing
Anti-Graffiti Coating
Online Plan Room
SSH will list subcontracting opportunities in a plan room on BuildingConnected. While we get the plan room ready, please review your company profile on BuildingConnected to ensure contact information and scopes of work are up to date.